Orbital context

Plots are in GSE (geocentric solar ecliptic) coordinates, so Earth is at [0,0], the Sun is at [1,0]. The plot is the projection of the orbit on the ecliptic plane.

Animated Version: Orbit_LTP02.mp4

New definition for the grey shading representing downlink rates:

  • white = maximum downlink rate at which you can empty the SSMM in ~10 days
  • light-grey = SSMM fill state decreases with everyone operating at EID-A rates
  • mid-grey = SSMM fill state increases within RSW (10 instruments operating) and decreases outside RSW (IS-only breakeven rate < downlink rate < inside-RSW breakeven rate )
  • dark-grey = SSMM fill state increases with just IS operating (downlink rate < IS-only breakeven rate)

RS checkout window placement

Period

Window/GAM

EXT Start

Start

End

Heliocentric

Distance

Range

Heliographic

Latitude

Range

SC-Sun-

Earth

Angle

Conjunction

Safe Mode Comms Blackout

Largest Comms Roll

GAM Restrictions

LTP 02N/A













0 (TBC)

GAMs and conjunctions

  • Venus GAM on 2020-12-27, GAM restriction period expected to run from 2020-11-29 to 2021-01-03. 

Science and calibration planning

IS science only: (updated at SOWG#14)

  • IS modes: As the spacecraft is moving rapidly away from Earth, IS observation modes have to be switched to low rates modes around mid August 2020 the latest. Mid Dec 2020 they can be switched again to normal science modes.
    At SOWG#14 (after MAG proposal at SWT#14) it was decided to support PSP perihelion on 27 Sep 2020 by reintroducing ~4 weeks of IS normal modes around that time. To compensate, the low-rate period has been updated to start ~2 weeks early and end ~2 weeks later. 
  • MAG calibration roll: to be scheduled in July 2020 (heliocentric distance between 0.55 and 0.77 AU) 
  • RS payload is IDLE or OFF (to be confirmed, currently modelled as IDLE)

Coordinated campaigns:

  • IS operations coordinated with PSP to support its 6th perihelion passage - see above.


SOOP Kitchen plan