DateMeetingPreparation for ...Planning Activity or SGS TestOutput of ... / Feedback on ...
Jan 2017SOWG 9

Focus on Procedures and IORs

Discuss E2E test schedule.

None





GFTS compatibility tests with example IORs

SWT Comments on V0 SAP

April 2017
(Granada) 

SWT 20


  • SWT: Mission Level Planning of Cruise
  • SOC: Inputs for LTP exercise, FECS, SPKT
  • PS/SOC prepare SAP v1 (link)




July 2017SOWG 10

2nd LTP exercise with SOOP Kitchen (link to plan) (presentation1 & 2):
6 months in Cruise, 1 RS checkout in detail
(input to E2E-0)






SOC prepares LTP output: E-FECS & TM Corridors
Oct 2017
(US) 
SWT 21


Jan 2018SOWG 11

MLP of Cruise Phase (Launch Feb 2020) with SOOP Kitchen (link to plan) (with permission from SWT) 

documented on MLP of Cruise during SOWG#11




Preparation E2E-0 test:

  • Instrument teams write STP IORs

  • SOC reviews STP IORs as input for E2E0



April 2018
(Paris) 
SWT 22

PSP coordination during Cruise:

  • what are the main opportunities to coordinate with PSP?
  • what type/quality of RS observations are needed to support these campaigns?





0th End to End Test (STP) (excl MOC)
July 2018SOWG 12

none

Outcome of and feedback on E2E-0 test (link to test report)


Aug 18PSP launch


Nov 2018
(FNHW)

SWT 23

Prepare input to LTP exercise (=MLP for 6 months NMP):



Prepare PSP coordination during Cruise:

  • Discuss location of PSP coordination opportunities during Cruise - choose best ones




Preparation LTP exercise:



Jan 2019

SOWG 13


SOWG 13 LTP Exercise Science Orbit (Launch Feb 2020)
following SAP input provided by SWT


mini-SWT
(attached to
SOWG13)

Preparation Cruise Phase MLP(1) - see MLP of Cruise during mini-SWT







Output LTP exercise:

  • SOC distributes formal products (EFECS, TMC, obs timelines)
    and context plan in SOOP Kitchen
  • = input for IOR writing for E2E-1 test

2-4 April 2019 (Firenze)

~9m before Jan-Jun 2020

SWT 24
Cruise Phase MLP (1): Plan Cruise Phase (incl PSP coordination)
& freeze SAP for Feb-June 2020 (see MLP of Cruise during SWT#24)
(Launch Feb 2020)

Feedback on PSP coordination discussions (as input into MLP planning)


(Jun 2019:
ESTRACK meeting)

Preparation LTP01 LTP02 :

  • Instrument teams review observation definitions for Cruise in SOOP Kitchen
  • MOC sends FECS and PTEL station schedule for LTP 1 to SOC
  • SOC prepares SOOP Kitchen (obs definitions, event timeline, ...)

Output MLP 1:

  • SOC prepares pass requests for May-June 2020
  • MOC formally requests passes from ESTRACK (to be fed into FECS)

Preparation E2E-1 test: (context in E2E-1 area)

  • Preparation of SOC subsystems and interfaces with ITs and MOC for E2E-1

  • Instrument teams write STP IORs

  • SOC reviews STP IORs as input for E2E-1




1st End to End Test with MOC (STP)  (ST_E2E_01 - Test Report)

10-11 Jul 2019

6m before Jan-Jun 2020

SOWG 14
Cruise Phase LTP01  & LTP02 :
observations and SOOP planning for Feb-JuneDec 2020 (link to SOOP Kitchen plan)
(Launch Feb 2020)
Feedback on E2E-1 test (presentation)


Preparation Cruise Phase MLP(2): (2nd half 2020 has been planned already)

  • Review PSP coordination (opportunities from Jul 2020 onwards)
  • SOC prepares context for Cruise Phase planning (orbit plots, events, ...)

Output LTP 1&2 planning - Indicative only! (no formal FECS yet)

  • SOC distributes indicative LTP products (EFECS, TMC, obs timelines) to instrument teams
    and context plan in SOOP Kitchen
  • = input for IOR writing for MTP-1

16-17 Oct 2019 (ESTEC)

9m before Jul-Dec 2020

SWT 25

Cruise Phase MLP (2): revision of MLP for Cruise
& freeze SAP for Jul-Dec 2020

See MLP of Cruise during SWT#25 (Oct 2019)
(Launch Feb 2020)


(Jan 2020:
ESTRACK meeting)

Preparation LTP 2 - (LTP2 was planned at SOWG14, no new input)

  • Instrument teams review observation definitions for Cruise in SOOP Kitchen
  • MOC sends FECS station schedule for LTP 2 to SOC
  • SOC prepares SOOP Kitchen (obs definitions, (E-)FECS, ...)

Output MLP 2:

  • SOC prepares pass requests for Jul-Dec 2020 + calibration roll requests 
  • MOC formally requests passes from ESTRACK (to be fed into FECS)
Nov-Dec 2019

Delta End to End 1 Test (STP)

Part 1: rerun E2E-1 with the same IORs but using updated STP subsystem and new filenames for SOC-MOC interface
(Instrument teams not directly involved)


2-3 Feb 2020 (Cape Canaveral)

10m before Jan-Jun 2021

SWT 26
No formal planning as SC has not been launched, yet no new input.
MLP planning will be postponed to mini-SWT in March 2020, attached to SOWG15. 

FEB 2020 LAUNCH