Date | STP-100 Event or Deadline | STP-101 Event or Deadline | Comments |
---|---|---|---|
NOTES: | STP-100 runs from 15 to 22 June 2020 and includes RSCW1. IORs from all 10 instruments are expected. | STP-101 runs from 22 to 29 June 2020. Unless some RS operations from RSCW1 still have be closed out, only IORGs from IS instruments are expected. | |
5 May 2020 | Distribution of new MIB by MOC | SOC will forward via GFTS | |
7 May 2020 | Distribution LTP01 output to instrument teams: EFECS, TM corridors and JSON timelines | Distribution LTP01 output to instrument teams: EFECS, TM corridors and JSON timelines | via GFTS |
8 May 2020 | Open IOR delivery window for IORs, based on MIB of 5 May | Instrument teams that do not rely on updates can start preparing IORs and delivering IORG via GFTS | |
15 May 2020 (TBC) | Distribution of final MIB by MOC | Distribution of final MIB by MOC | SOC will forward via GFTS |
ASAP afterwards | SOC updates STP environment, to allow delivery of IORs relying on final MIB | Open IOR delivery window for IORs, based on final MIB | All instrument teams can prepare IORs and deliver IORG via GFTS |
22 May 2020 | Deadline for first version of IORs | Deadline for first version of IORs | This deadline is set to allow for iterations with instrument teams in case of problematic IORs or problems in SOC model. Note IORs for STP-101 should always be delivered after IORs for STP-100. |
29 May 2020 | Deadline final version IORs | Deadline final version IORs | SOC starts final check and consistency of all IORs, and prepares PORs for MOC Note IORs for STP-101 should always be delivered after IORs for STP-100. |
1-2 June 2020 | First POR bundle to MOC | Early deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed | |
9 June 2020 | First POR bundle to MOC | Early deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed | |
10 June 2020 | Deadline final version PORs to MOC | ||
15 June 2020 | Start of STP-100 onboard | ||
17 June 2020 | Deadline final version PORs to MOC | ||
22 June 2020 | Start of STP-101 onboard |
Overview
Content Tools
Apps
Tasks
1 Comment
Luis Sanchez
Maybe we have to put a big red notice at the top of the table stating that the MIB to be used for STP-100 and -101 (delivered, hopefully, on 15 May) will be also the one to be used for STP-200 and -201 because we will a very short turnaround time from FD deliveries to opening IOR delivery windows.
Do we need to remark on the star calibration during STP-100?