STP-102 runs from 29 June to 6 July 2020 (DOYs 181-188) and includes only IS operations. Therefore only IORGs from the 4 IS instrument teams are expected  + SPICE for CMS.


DateEvent or Deadline Comment
9 June 2020Distribution LTP02 output (EFECS, JSON, TMCs) to instrument teamsvia GFTS
11 June 2020Open IOR delivery window for IORsInstrument teams can start delivering IORGs via GFTS - CRRs will be returned automatically (only checking for format issues)
Wed 17 June 12UTIOR deadlineSOC starts final check and consistency of all IORs, and prepares PORs for MOC
19 June 2020First POR bundle to MOCEarly deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed
Wed 24 June Deadline final version PORs to MOC
29 June 2020Start of STP-102 onboard


MIB version to be used: MIB__20200603M15520PFMS001_SOL.zip. This MIB is similar to MIB__20200515 but contains a few updates for PHI, Metis and SWA.

Full overview of MIB versions and applicability: MIB and FOP


  • No labels