STP-104 runs from 13 to 20 July 2020 (DOYs 195-202). Only IORGs from IS instruments are expected + SPICE for CMS.
Date | Event or Deadline | Comment |
---|---|---|
9 June 2020 | Distribution LTP02 output (EFECS, JSON, TMCs) to instrument teams | via GFTS |
26 June 2020 | Open IOR delivery window for IORs | Instrument teams can start delivering IORGs via GFTS - CRRs will be returned automatically (only checking for format issues) |
Wed 1 Jul 12UT | IOR deadline | SOC starts final check and consistency of all IORs, and prepares PORs for MOC |
3 July 2020 | First POR bundle to MOC | Early deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed |
Tue 7 July | Deadline final version PORs to MOC | |
13 July 2020 | Start of STP-104 onboard |
MIB version to be used:
Overview of all MIB versions and applicability: MIB and FOP