STP-104 runs from 13 to 20 July 2020 (DOYs 195-202). Only IORGs from IS instruments are expected + SPICE for CMS.

DateEvent or Deadline Comment
9 June 2020Distribution LTP02 output (EFECS, JSON, TMCs) to instrument teamsvia GFTS
26 June 2020Open IOR delivery window for IORsInstrument teams can start delivering IORGs via GFTS - CRRs will be returned automatically (only checking for format issues)
Wed 1 Jul 12UTIOR deadlineSOC starts final check and consistency of all IORs, and prepares PORs for MOC
3 July 2020First POR bundle to MOCEarly deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed
Tue 7 JulyDeadline final version PORs to MOC
13 July 2020Start of STP-104 onboard


MIB version to be used: 

Overview of all MIB versions and applicability: MIB and FOP