STP-105 runs from 20 to 27 July 2020 (DOYs 202-209). Only IORGs from IS instruments are expected + SPICE for CMS + SoloHI for a first straylight assessment.

DateEvent or Deadline Comment
9 June 2020Distribution LTP02 output (EFECS, JSON, TMCs) to instrument teamsvia GFTS
1 July 2020Open IOR delivery window for IORsInstrument teams can start delivering IORGs via GFTS - CRRs will be returned automatically (only checking for format issues)
Wed 8 July 12UTIOR deadlineSOC starts final check and consistency of all IORs, and prepares PORs for MOC
10 July 2020First POR bundle to MOCEarly deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed
Tue 14 July 2020Deadline final version PORs to MOC
20 July 2020Start of STP-105 onboard


MIB version to be used: 

Overview of all MIB versions and applicability: MIB and FOP