STP-107 runs from 3 to 10 Aug 2020 (DOYs 216-223). Only IORGs from IS instruments are expected + EUI for part 1 of the NECP-remaining activities.
Date | Event or Deadline | Comment |
---|---|---|
9 June 2020 | Distribution LTP02 output (EFECS, JSON, TMCs) to instrument teams | via GFTS |
Thu 16 July | Open IOR delivery window for IORs | Instrument teams can start delivering IORGs via GFTS - CRRs will be returned automatically (only checking for format issues) |
Wed 22 July 12UT | IOR deadline | SOC starts final check and consistency of all IORs, and prepares PORs for MOC |
24 July 2020 | First POR bundle to MOC | Early deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed |
Tue 28 July 2020 | Deadline final version PORs to MOC | |
3 Aug 2020 | Start of STP-107 onboard |
MIB version to be used:
Overview of all MIB versions and applicability: MIB and FOP