STP-108 runs from 11 to 17 Aug 2020 (DOYs 223-230). Only IORGs from IS instruments are expected + SPICE for CMS.
Date | Event or Deadline | Comment |
---|---|---|
9 June 2020 | Distribution LTP02 output (EFECS, JSON, TMCs) to instrument teams | via GFTS |
Wed 22 July | Open IOR delivery window for IORs | Instrument teams can start delivering IORGs via GFTS - CRRs will be returned automatically (only checking for format issues) |
Wed 29 July 12UT | IOR deadline | SOC starts final check and consistency of all IORs, and prepares PORs for MOC |
31 July 2020 | First POR bundle to MOC | Early deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed |
Tue 4 Aug 2020 | Deadline final version PORs to MOC | |
10 Aug 2020 | Start of STP-108 onboard |
MIB version to be used:
Overview of all MIB versions and applicability: MIB and FOP