STP-109 runs from 17 to 23 Aug 21:50 (!!) (DOYs 230-236). Only IORGs from IS instruments are expected + SPICE for CMS.

DateEvent or Deadline Comment
9 June 2020Distribution LTP02 output (EFECS, JSON, TMCs) to instrument teamsvia GFTS
Wed 22 JulyOpen IOR delivery window for IORsInstrument teams can start delivering IORGs via GFTS - CRRs will be returned automatically (only checking for format issues)
Wed 5 Aug 12UTIOR deadlineSOC starts final check and consistency of all IORs, and prepares PORs for MOC
Fri 7 Aug 2020First POR bundle to MOCEarly deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed
Tue 11 Aug 2020Deadline final version PORs to MOC
17 Aug 2020Start of STP-108 onboard


MIB version to be used: 