STP-111 runs from 31 Aug to 7 Sep 2020 (DOYs 244-251). IORGs from all instruments are expected: IS IORs for operations + RS IORs for switching the instruments OFF in time for MAINT activity.
Date | Event or Deadline | Comment |
---|---|---|
9 June 2020 | Distribution LTP02 output (EFECS, JSON, TMCs) to instrument teams | via GFTS |
Wed 13 Aug | Open IOR delivery window for IORs | Instrument teams can start delivering IORGs via GFTS - CRRs will be returned automatically (only checking for format issues) |
Wed 19 Aug 12UT | IOR deadline | SOC starts final check and consistency of all IORs, and prepares PORs for MOC |
21 Aug 2020 | First POR bundle to MOC | Early deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed |
Tue 25 Aug 2020 | Deadline final version PORs to MOC | |
31 Aug 2020 | Start of STP-111 onboard |
MIB version to be used:
Overview of all MIB versions and applicability: MIB and FOP