STP-111 runs from 31 Aug to 7 Sep 2020 (DOYs 244-251). IORGs from all instruments are expected: IS IORs for operations + RS IORs for switching the instruments OFF in time for MAINT activity.

DateEvent or Deadline Comment
9 June 2020Distribution LTP02 output (EFECS, JSON, TMCs) to instrument teamsvia GFTS
Wed 13 AugOpen IOR delivery window for IORsInstrument teams can start delivering IORGs via GFTS - CRRs will be returned automatically (only checking for format issues)
Wed 19 Aug 12UTIOR deadlineSOC starts final check and consistency of all IORs, and prepares PORs for MOC
21 Aug 2020First POR bundle to MOCEarly deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed
Tue 25 Aug 2020Deadline final version PORs to MOC
31 Aug 2020Start of STP-111 onboard