Note: STPs 133 to 134 are affected by a superior conjunction. Therefore the STPs 133 to 135 have unusual deadlines.

STP cycleIOR delivery opensIOR deadlinePOR deadline (on SOC)Planned uplink by MOCStart of STP cycle onboardCommentsSOC responsible
132Thu 7 JanWed 13 Jan 12UTTue 19 Jan uplink on 22 JanSun 24 Jan 21:10:44
(DOY 24)

IORs expected from IS + STIX + SPICE CMS  + PHI switch ON


133

Wed 13 Jan 

(EUI MIB update on 18 Jan)

Tue 19 Jan 12UT

(20 Jan for EUI)

Fri 22 Januplink on 27 Jan (backup 29 Jan)Mon 1 Feb 
(DOY 32)
IORs expected from IS + STIX + SPICE CMS + PHI & EUI synoptics

Note conjunction during STP.

Note EUI will do SW upload before this STP (19-22 Jan). EUI needs to use updated MIB (to be released 18 Jan).

134

Wed 13 Jan 

(EUI MIB update on 18 Jan)

Tue 19 Jan 12UT

(20 Jan for EUI)

Fri 22 Januplink on 27 Jan (backup 29 Jan)Mon 8 Feb 
(DOY 39)

All payload (RS synoptics)

Note early IOR and POR deadlines because commanding cannot be uploaded during conjunction!

135

Wed 13 Jan 

(EUI MIB update on 18 Jan)

Tue 19 Jan 12UT

(22 Jan for EUI)

Tue 26 Jan 12UTuplink on 29 Jan (backup 12 Feb)Mon 15 Feb 
(DOY 46)

All payload (RS synoptics = start RSCW2)

Note early IOR and POR deadlines because commanding cannot be uploaded during conjunction!

136Wed 13 Jan Wed 10 Feb 12UTTue 16 Feb
Mon 22 Feb 
(DOY 53)

All payload (2nd half RSCW2)

SOC will open IOR delivery window early, so that RSCW2 commanding can be prepared in one go.

Jayne Lefort

All dates in 2021.


MIB version to be used: 

Overview of all MIB versions and applicability: MIB and FOP