LTP4 Block | STP cycle | IOR delivery opens | IOR deadline | STP POR deadline (on SOC) | Planned uplink by MOC | MIBs | Start of STP cycle onboard | Comments | SOC ESA responsible | Main operator |
---|---|---|---|---|---|---|---|---|---|---|
2 | 158 | Wed 7 July | Wed 14 July (1200 ) | Tue 20 July (12:00) | Assumed Saturday | on MIB from stp157 | (22:00) | TCM type 2 IS, SPICE CMS and STIX ANALYSIS. SOLOHI will be off (not sending IORs) until STP160. | SCO-2 | |
159 | Wed 7 July | Wed 21 July (1200 ) | Tue 27 July (12:00) | Assumed Saturday | (19:00) | TCM type 2; SA ROTATION IS, SPICE CMS (x2) and STIX ANALYSIS. SOLOHI will be off (not sending IORs) until next STP period. | ||||
160 | Wed 7 July | Tue 27 July (12:00) | Friday 30 July (12:00) PORS by 2 Aug latest | Assumed Tuesday | (21:00) | TCM IS, SPICE CMS, SOLOHI EXT window for venus observations (must be off though for VGAM, despite ext window overlapped with VGAM MAINT window – switches ON during 2021-08-07T14:58:00 EMC_PREF_NOISY). | ||||
161 | Wed 7 July | Thurs 29 July (08:00) | Tue 3 Aug (12:00) | Assumed Saturday aim for 6/8 | (15:15) | During VGAM, the RS instruments have to be switched off, this includes METIS, PHI, SOLOHI, STIX, SPICE OU and EUI OU. SPICE CMS IS OK. SoloHI switches OFF 2021-08-09T04:00:00 before the VGAM 2 window Note that following the VGAM, SWA HIS&EAS and SPICE OU cannot be switched back on until at least 1h after closest approach SPICE deco heater commanding needed in HSD POR because of VGAM. Outside of MAINT, STIX ANALYSIS and CMS | ||||
3 | 162 | Wed 28 July config update (SPICE/PHI) needed after window opening | Tue 3 Aug (1700) Later for PHI and SPICE | Wed 11 Aug (11:00 UTC) | Assumed Wednesday | MIB (SPICE/PHI/STIX/SWA/HI) update on OPSLAN aim for MIB deployment after uplink of products for STP16) on 6/8 before the CEB pass starting at 09:12 UTC. TBC depends on VGAM. | (06:00) | TCM, Roll manoeuvre, IS, Pre EXT window, SPICE CMS , SPICE functional (SPICE deco heater commanding needed in HSD POR because SPICE HSD opens AND closes in this STP). RS EXT windows lots of RS ops, also HSD operations and METIS TAC. CFG needed after window opening | SCO-2 | |
163 | Wed 28 July EUI MIB not needed until 164 | Wed 11 Aug (12:00) Later for EPD (EUI should not have IORs) | Tue 17 Aug (12:00) | Assumed Friday | MIB (EUI) Update Available 13th Aug, SOC can wait until 164 |
| TCM IS observations Note deco heater may have to be turned off again because of SPICE observing. PHI + EUI FSW update through PDORs, coordinated by MOC (23 and 25 Aug passes) | SCO-2 | ||
4 | 164 | Thursday 12 Aug | Wed 18 Aug (12:00) | Tue 24 Aug(12:00) | Assumed Friday(12:00) |
| TCM, MAINT SA_RELUBRICATION IS, RS EXT windows lots of RS ops, also HSD operations and RPW TAC | Jayne Lefort | SCO-2 | |
165 | Thursday 12 Aug | Wed 25 Aug (12:00) | Tue 31 Aug(12:00) | Assumed Friday |
| MAINT ANY IS, RS /RS EXT windows lots of RS ops, also HSD operations. PHI TCA, SPICE TAC, EUI TAC, | ||||
166 | Thursday 12 Aug | Fri 3 Sep (12:00) | Thurs 9 Sep(12:00) | Assumed Monday |
| IS, RS windows lots of RS ops, also HSD operations. VTSP updates | ||||
167 | Thursday 12 Aug | Wed 8 Sep (12:00) | Tue 14 Sep(12:00) | Assumed Friday | (23:00) | IS, RS EXT windows lots of RS ops, also HSD operations. | everyone |
All dates in 2021, UTC