STP-102 runs from 29 June to 6 July 2020 (DOYs 181-188) and includes only IS operations. Therefore only IORGs from the 4 IS instrument teams are expected + SPICE for CMS.
Date | Event or Deadline | Comment |
---|---|---|
9 June 2020 | Distribution LTP02 output (EFECS, JSON, TMCs) to instrument teams | via GFTS |
11 June 2020 | Open IOR delivery window for IORs | Instrument teams can start delivering IORGs via GFTS - CRRs will be returned automatically (only checking for format issues) |
Wed 17 June |
12UT | IOR deadline | SOC starts final check and consistency of all IORs, and prepares PORs for MOC |
19 June 2020 | First POR bundle to MOC | Early deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed |
Wed 24 |
June | Deadline final version PORs to MOC | |
29 June 2020 | Start of STP-102 onboard |
MIB version to be used: MIB__20200603M15520PFMS001_SOL.zip. This MIB is similar to MIB__20200515 but contains a few updates for PHI, Metis and SWA.
...